Follow the progress of Cornerstone's Big Spring Branch Slated to Open in the Spring of 2012
April 19, 2012


Finishing touches to the roof; ready for parking and exiting
April 16, 2012

Full steam ahead with blacktop
April 10, 2012


Beginning the blacktop; view from behind the teller line; lobby area
April 4, 2012

View from the drive thru and from the road
March 13, 2012

Preparing for drywall, back side of building, view from backyard
February 23, 2012

Curbing uncovered, brick walls and finished roof
February 7, 2012
Front doors, electric wiring and curbing
December 22, 2011


More excavating and drive through area
December 13, 2011


The roof is on and the inside walls are framed
December 8, 2011


Starting the roof and laying water lines
November 30, 2011

The walls go up
November 11, 2011


Preparing for footers
October 2011

Ground Breaking Ceremony

Building Plan Empty Lot |